Friday, July 6, 2012

Dirty Thursdays 6/21 - 7/5



During the last few weeks Dirty Thursday crews have moved back onto the yellow trail to address some touch-ups to eroding areas and some minor re-routes to fall line sections.

The most recent re-route was originally to be placed across a grassy 20% side slope to the east of the trail, which was in a 35% fall line. As Art and I were laying out a turn for pin flagging, Art noticed we had drifted too close to another trail in this narrow corridor. Art quickly looked for another option on the other side of the trail which was much more rocky. Although there was a tad more work needed on the other side, the result was fantastic, as the trail now passes through areas of glacial erratics, ferns and rock features.

One thing that Art and I have learned is to keep an open mind with the route. Sometimes a trail designer can find what they think is the holy grail of routes, but one small part of that route is not right in design. Many times we have had to abandon our plan and rethink options, until we find a better solution. The final result has always been better than the first plan. This is why taking our time with planning is very important for us. After spending most of our trail building years maintaining poorly designed trails, we have developed a greater appreciation for a well designed trail.






volunteers: Manny and Jeff that braved the heat to work

After last nights build, I rode out of the woods as the sun set to my west. What was a very hot day, was now surprisingly comfortable in the the shade of the woods with the occasional gentle breeze. As I rode down the final trail before reaching the lot, my shoes bouncing back and forth tied to my pack, the sun washed the woods orange leaving only my shadow in front of me. I felt thankful to be riding my bike, a little sweaty, covered in dirt, and there at that exact moment.

-Ellen

Friday, June 15, 2012

Dirty Thursdays May 27 - June 14



During the last few weeks volunteers have helped to build a series of re-routes on the Cannonball Trail alternate near the radio tower. The trail actually splits at this point, as the NYNJTC re-routed a section a few years back, leaving the old section intact. Our work was on the old section and is now open for traffic in both directions.

The lower section was a pleasure to bench cut, as there were very few rocks in the soil ...a very rare circumstance in Ringwood.

We would like to thank these volunteers:
Joe Esak
Gavin Spray
James Wilbur
Adrienne Blair
Jeff Martz
Anfernee Goon
Tom Stanowski
Henry Gozdz
Marianne Sanagelo
Brad Turner
Patti Duffy
Blair Stearns


snakeskin found while working



- Art and Ellen

Friday, May 18, 2012

Dirty Thursdays April 26 - May 17


Ringwood/Ramampo Trail (red) Re-route progress: Art and I are happy to announce that all the re-routes and repairs on this project are complete. Three years ago, our first re-route was stared back in Ringwood State Park just beyond the Blue trail bridge crossing. We have worked our way several miles up the hill into Ramapo Mountain State Forest and are now complete where it intersects with the yellow blaze trail.

If you are out on the trail, please check out the recently completed re-route just opened last night. It winds around through rock outcrops and trees and gently traverses some tight terrain and avoids the steep wash out that was there before. Tags have been moved and old trail has been reclaimed. We hope to see blueberry bushes growing in the old trail next year. Thanks to Volunteers over the past few weeks: Mike Zusman, James Wilbur and Henry Gozdz.

On the upcoming Thursdays we will be working our way east and south towards Skyline Dr with some repair work on the Yellow and Cannonball. Please RSVP for location the day before.


Last night when I rode in, I was surprised to see some laurel blooming along the Cannonball trail. Middle of May is quite early. I usually remember the wash of pink surrounding the lakes in Harriman on the first week of June. So if you are out there to enjoy the flowers this year, get out a few weeks early. Later up the trail I spotted some sort of fragrant wild rose. Things are very lush right now, which may seem odd as we were close to a drought a month ago. On our way back, we had to clip face slappers the whole way. This is a great time of year to enjoy the woods. - Ellen



Friday, April 20, 2012

Dirty Thursdays April 12 & 19


Thanks to volunteers for giving 31 hours of work the past two Thursdays, a re-route on the Cannonball is blazed and open for riding and hiking. If this trail is on your agenda, please check it out in both directions. Blueberry bushes are budding and things are really turning green out there.


This section is blazed in cooperation with the NYNJTC trail marking system. It is a connector to the main bike route (red) between Ringwood State Park and Ramapo State Forest.


New trail crossing the old fall line trail.





Thanks to:
Connie Farley
Bryan Carbone
James Bazzano
Henry Gozdz
Dennis Efinov
Mike Zusman
JD Dodd
James Wilbur

Art and Ellen

Saturday, April 7, 2012

April 5 and 7 Trail Work



With all this wonderful weather, trail building progress has been outstanding! That being said, we really need rain as the ground is tinder dry very deep down. This is not typical for this time of year and forest fire danger is extremely high right now. Even if you do not see fire, if you see or smell smoke, please report it to the park (Ringwwod State Park (973)962-2240) or Forest fire service.



Thursday five volunteers finished up the next re-route on the Ringwood-Ramapo trail and are poised to start the next section. We will take a few week break on this trail and move to the Cannonball Trail for the next few Thursdays.

Today seven volunteers helped clear and bench cut several traversing turns on the Cannonball trail just north of the DPW site. The existing trail went straight down the fall line and had become nearly twenty feet wide. The new trail traverses the same hill. We plan to finnish this project on the next few Thursdays.


old fall line trail


new traversing trail

A lot got done done this past week. A big Thanks to our volunteers for 47 hours of work:
Henry Gozdz
James Wilbur
Tom Stanowski
Rich Gorman
Blair Stearns
Gail Dickard
Eric Ackerson

- Art and Ellen White

Saturday, March 17, 2012

March 17 Work Day



Ringwood - Ringwood/Ramapo Tr: Next section worked was just beyond the intersection of the Old Guard Tr (green/white). A small group of volunteers came out on this beautiful March day and got the bulk of this section done. A gap was filled to bridge onto a big slab, and the bottom of the slab was built up with a rock ramp. Also a small set of stairs for hikers was built and the lead up was bench cut. Looking good and may be opened up after a few Dirty Thursday sessions.


Before


After


Bridged gap, stairs to right

Thanks to volunteers that put in 39 hours:
Henry Gozdz
Willy Wilbur
Marianne Santangelo
Ted Haack
Ryan Hogan
- Art and Ellen

Monday, January 2, 2012

Ringwood-Ramapo Trail Progress - 2011



2011 wrap up: For those following the Ringwood-Ramapo (red blaze) project, we (Jorba) have been making improvements to a long section of trail from the intersection of the (blue) bridge all the way up to The Old Guard Trail (green/white) intersection. The project started with two years of planning and approvals, and then three years of actual re-route trail building to date. This trail traverses and climbs through some very extreme grades and numerous rocky areas. When Art and I first took on this project, we knew it was ambitious. Trying to keep volunteers motivated to work on something that they may not be able to ride for years was tough, but I think we have finally crested over the top of that hill in 2011, as the route is open for riding and hiking.

Throughout 2011 our Jorba volunteers came out to work nearly every Thursday from May through September plus several weekend super work days, putting in over 500 hours of volunteer labor. During these work days we have had a plethora of memorable experiences on this special mountain. We have worked in extreme heat, in clouds of mosquitoes and in thunderstorms. We have witnessed beautiful water falls from a year of heavy rains. We have been blessed with beautiful sunsets and gentle breezes. Every Thursday has been spent with hands in the dirt and moving rocks to create a pleasing path for others to take. We hope you will take it.









Jorba would like to thank these volunteers for donating their time and labor to work on Ringwood trails in 2011:
Joe Azze
Jo Baldacci
Joe Benevento
Ty Benevento
Adrienne Blair
James Bazzano
Steve Brossok
Zsuzanna Carlson
Allen Clark
Jessica Clark
Jeff Coneys
Joaquin Conizales
Elizabeth Corrion
Jeffrey Dodd
Leigh Dodd
Bill Dove
Pattu Duffy
Tim Egan
Joe Esak
Lori Esak
Tray Esak
Mike Ferraro
Chris Focacci
Chris Garatti
Phil Germakian
Henry Gozdz
Thomas Gustainus
Tom Haines
Steve Kleiber
Manny Lugo
Dan Matthews
Kathy Maziarz
Chris Michaloski
Randy Miller
Frank OReilly
Tom Pannorei
Darlene Phillips
Joe Prebish
Michael Rossi
Marianne Santagelo
Jennel Santos
Conor Schaar
Joe Schaar
Brian Sniatowski
Tom Stanowski
Tahir Thomas
Steve Wagoner
Tara Walhart
Art White
Ellen White
James Wilbur
Ben Williams
Joey Wyckoff
Mike Zusman